MOUNTAIN SKY INTERMEDIATE DISTRIBUTION FACILITY (IDF 1)
DETAILS

  - IDF 1 Scheme

Mountain Sky IDF1 details

  - IDF1 details:
      - The Intermediate Distribution Facility 1 (IDF1) must service 24 rooms requiring connection from Building A West and must also assure the backbone link with the MDF from Building A East
        - The type of cable used to connect these 24 rooms is CAT 5 UTP - this is the Horizontal Cross Connect (HCC) cable
         - The type of cable used to connect IDF 1 to MDF is Fiber Optic Multimode Cable - Backbone connection - Vertical Cross Connect (VCC) cable

  - IDF 1 equipment used:
        - for the 24+24 connections we will use the following equipment:
              - two 48-port Switches - only 24 ports on each switch will be used (also one 48-port switch would be enough but future expansion would need more ports available so using two 48-port switches would be very useful)
               - two 48-port Patch Panels for curriculum network (VLAN3-VLAN48)
               - one 24-port Patch Panel for teachers computers network (VLAN2)
               - VLAN 3 - VLAN48 patch panels will be named HCC 2 & HCC 3
               - VLAN 2 patch panel will be named HCC6
  - IDF Room details:
       -
The interior walls are painted with fire retardant paint and has 3/4" plywood which is raised 1 1/4" from the walls where equipment is mounted
       - 15 feet of wall space is provided for the POP terminations.
     - Drop ceiling should have fixed ceilings installed to prevent unauthorized access.
       - 12" ladder rack and 4" conduits installed for horizontal and vertical cabling.
      - Water and steam pipes should not run through or above the wiring closets and the humidity should be maintained between 30% and 50%.
       - HVAC should maintain the room temperature at 70 degrees F.
       - Incandescent lights have been installed

 